Right-of-Use and Wayleave Agreements in Malaysia
A company that needs to occupy, cross or run a pipeline or cable through land it does not own has four broad legal routes in Malaysia: a negotiated easement, a private right-of-use or licence agreement, a Temporary Occupation Licence over State land, or — for a licensed utility — a statutory wayleave. Which one applies decides a question that matters far more than most teams realise before they build: does the right survive if the landowner sells, and can it be enforced against whoever buys next.
Most industrial and infrastructure projects meet this problem the same way. A facility needs access across a neighbouring lot. A pipeline has to cross land the operator will never own. The site itself sits on land held under a short-term arrangement with the state. Someone gets a verbal yes, a consent letter, or an informal understanding with whoever owned the land at the time — and the arrangement gets papered later, if it gets papered at all. That works until the land changes hands, the term nobody wrote down runs out, or the new owner wants to renegotiate from a position the operator no longer controls.
What legal instruments give a company the right to use or cross land it doesn't own?
Malaysian law offers several distinct routes, and they are not interchangeable — each has a different creation process, a different answer on whether it binds a future owner, and a different compensation basis.
Instrument | Legal basis | How it is created | Binds a buyer of the land? | Typical term |
|---|---|---|---|---|
Registered easement | National Land Code 1965, Part Seventeen (ss.282–292) | Express grant by the landowner, registered against the title | Yes, once registered | Time-limited or perpetual, as granted |
Land Administrator's right of way | National Land Code 1965, Part Twenty-Eight (ss.387–395) | Application to the Land Administrator where the owner will not agree voluntarily | Yes — a statutory right attaching to the land | As fixed on creation; can be varied or extinguished under the same Part |
Private right-of-use or licence agreement | General contract law (Contracts Act 1950) | Negotiated agreement between the parties, not registered | No — personal to the parties unless the buyer separately agrees to honour it | As drafted; usually fixed with renewal options |
Temporary Occupation Licence (State land) | National Land Code 1965, ss.65–69 | Issued by the Land Administrator (or State Authority route) over State, mining or reserved land | No — not assignable and does not pass on death | Expires with the calendar year issued; renewable annually, capped at three renewals without State Authority approval |
Statutory utility wayleave | Sector legislation, e.g. Electricity Supply Act 1990, ss.11, 13 and 16 | Notice by the licensee; the landowner can object, triggering a Land Administrator's inquiry | Runs with the licensee's statutory power, independent of ownership | Continues for as long as the installation remains, subject to maintenance rights |
The instruments that get registered or arise by statute survive a sale of the land. The ones that do not — most private right-of-use agreements, and Temporary Occupation Licences — are only as good as the party who signed them, and stop being useful the moment that party is no longer the owner.
Easement or private right-of-use agreement — which one do you actually need?
An easement under the National Land Code requires an express grant — Malaysian law does not recognise an easement arising informally or by long use in the way some common-law jurisdictions do. Section 282 defines what counts as an easement; section 284 sets out the requirement for express grant; and once granted in the prescribed form and registered against the servient title, the right binds the land itself, not just the person who granted it. That registration step is what makes an easement durable — the project's access or crossing right does not evaporate because the underlying land is sold, inherited, or charged to a bank.
Two adjacent questions usually come up at the same point in this process: see build-operate-transfer and concession agreements and consortium agreement for government tenders for how each is handled.
A private right-of-use or licence agreement is faster to put in place and does not require the landowner's cooperation with a registration process — but it is a personal contract, not an interest in land. If the landowner sells, the buyer is not automatically bound by it, and the operator's only recourse is against the original counterparty, who by then may have taken the sale proceeds and moved on. This is the exact failure the National Land Code's Part Twenty registration regime exists to prevent for registered interests — section 340 provides that registration confers indefeasible title or interest, except in defined circumstances, which is the statutory reason a registered easement outlives a change of ownership and an unregistered licence does not.
Where the landowner will not agree to grant an easement voluntarily — most often because the land would otherwise be landlocked or the access is genuinely necessary — the National Land Code gives a fallback: an application to the Land Administrator for a right of way under Part Twenty-Eight. This is a statutory mechanism, not a negotiation, and it comes with its own compensation and cost-allocation rules rather than whatever the parties agree between themselves.
What is a Temporary Occupation Licence, and when does it apply instead?
Where the site itself sits on State land, mining land not currently used for mining, or reserved land not currently used for its reserved purpose, the State Authority can permit occupation under a Temporary Occupation Licence rather than alienating the land outright. Under section 67, a licence normally runs only to the end of the calendar year in which it is issued, and can be renewed annually — but not more than three times without the State Authority's prior written approval. Section 68 is the point that catches operators out: a Temporary Occupation Licence is not capable of assignment and does not pass on the licensee's death, so it cannot simply be transferred to a new corporate vehicle, a financier, or an acquirer the way a registered interest can.
For a facility, plant, or long-lived piece of infrastructure, a licence that resets annually and cannot survive a corporate restructuring is a real constraint on financing and on any future sale of the business — it needs to be priced into the deal, not discovered during due diligence on an acquisition.
What compensation is payable for a wayleave or right-of-use over private land?
Where a licensed utility exercises a statutory power to lay or maintain lines over private land — the position for electricity supply under sections 11 and 13 of the Electricity Supply Act 1990 — the licensee must give notice before entering, the landowner has a window to object, and if no agreement is reached the amount of compensation is assessed by the District Land Administrator under section 16, with a right of appeal to the State Authority. Reported compensation disputes under this mechanism have distinguished between three categories of loss: disturbance to structures, damage to vegetation or other assets with an economic value, and disability — the reduced usefulness of the land area affected by the installation itself.
A negotiated easement or private right-of-use agreement is not bound by that statutory framework and can fix compensation however the parties agree — a lump sum, an annual payment, or a mix — but the same three heads are a useful checklist for what a properly drafted agreement should actually price: the disturbance caused by construction, ongoing damage from maintenance access, and the permanent reduction in what the landowner can do with the affected strip.
What does it cost to get this wrong?
The exposure shows up at three points. First, at the point of sale: an unregistered right-of-use arrangement does not automatically bind a purchaser, so a change of ownership can put an operating facility's access or crossing rights back into a negotiation the operator no longer controls — often after capital has already gone into the ground. Second, at renewal: a Temporary Occupation Licence that lapses because the three-renewal cap was missed, or because State Authority approval for a further renewal was not sought in time, can suspend lawful occupation of the site itself. Third, at handover: reinstatement and third-party damage obligations that were never defined in the original agreement become a dispute precisely when the relationship between the parties is ending, not before.
None of these are defects in the underlying law — they are gaps in how the instrument was chosen and drafted. The fix is deciding, before the site is built or the line is laid, which of the available instruments actually gives the durability the project needs, and pricing the extension, transfer, and reinstatement terms into the agreement from the outset rather than negotiating them under pressure later.
Frequently Asked Questions
Is a right-of-use agreement the same as an easement?
No. An easement is a registered interest in land created under Part Seventeen of the National Land Code and binds successors in title. A right-of-use agreement, unless it takes the specific form of a registered easement, is usually a personal contract that binds only the parties who signed it.
What happens if the landowner sells the land while my right-of-use agreement is still running?
If the right was never registered, the buyer is not automatically bound by it. This is the central risk with an unregistered arrangement, and it is why the choice of instrument — easement, statutory right of way, or private licence — should be made deliberately rather than by default.
Can a right-of-use agreement be registered on the title?
Sometimes, depending on the form the right takes and the category of the land involved. Where registration is available, taking it is usually what converts a right that can be lost on a sale into one that survives it.
What is a Temporary Occupation Licence, and is it the same as an easement?
No. A Temporary Occupation Licence under sections 65 to 69 of the National Land Code is a short-term permission to occupy State, mining or reserved land, renewable annually up to a statutory cap, and it cannot be assigned or transmitted on death. An easement is a registered right over land that survives a change of ownership. The two solve different problems.
Who pays for the right to lay a pipeline or cable across someone else's land?
Where a licensed utility is exercising a statutory wayleave power, compensation is assessed under the relevant sector legislation if the parties cannot agree it themselves. Where the arrangement is a negotiated easement or private agreement, compensation is whatever the parties agree — but it should be priced against the same disturbance, damage and disability categories a statutory assessment would use.
We have an existing right-of-use arrangement expiring soon — can it be extended?
Usually, yes, but the extension mechanism needs to be built into the instrument rather than assumed. A Temporary Occupation Licence has a hard cap on renewals without State Authority approval; a private agreement only extends on the terms it actually contains.
Getting this documented properly
A right of use that cannot survive a sale of the land, or a licence that lapses on its own renewal cap, is a risk that sits underneath the project rather than in front of it — which is exactly why it tends to surface at the worst possible moment. Legal That Works advises operators, developers and statutory bodies on right of use and land rights agreements — reviewing the title and land category, advising on the legal form the right should take, and drafting the extension, transfer-protection and reinstatement terms that decide whether the arrangement holds when the land changes hands. If capital is going into a site you do not own, get the instrument confirmed before the works start, not after the landowner has sold.
This article is for general information only and does not constitute legal advice. Every transaction and every set of facts is different. Obtain specific advice from a qualified adviser before acting on any part of it.
Related guides
Disclaimer
The content provided on this website is intended for general informational and educational purposes only. It does not constitute legal advice, nor should it be relied upon as a substitute for professional consultation with a qualified lawyer. Every legal matter is unique, and you are strongly encouraged to seek tailored legal advice from a licensed legal practitioner before taking any action based on the information available here.
While we endeavour to ensure the accuracy and timeliness of the content, ASCOLAW and its affiliates make no representations or warranties of any kind, express or implied, about the completeness, accuracy, reliability, suitability or availability of the information contained on this website. Any reliance you place on such information is strictly at your own risk.
Author
AKMAL SAUFI MOHAMED KHALED
Managing Partner & Founder
Practice Area
Corporate Real Estate
Project & Utilities
Real Estate
Business Function
Related Post
Right-of-Use and Wayleave Agreements in Malaysia


